Oregon regulators have approved a new Oregon data center tariff framework for Pacific Power, placing the largest new data centers in their own customer class and requiring them to pay the grid costs they cause. The Oregon Public Utility Commission (PUC) approved a settlement in docket UE 463 in mid-November 2026, and the framework is reported to take effect on 1 January 2027. It is the second such ruling under the state’s POWER Act, after Portland General Electric’s large-load tariff in May.
| At a glance | |
|---|---|
| Name / number | Pacific Power large-load (data center) framework, Oregon PUC docket UE 463 |
| Issuing body | Oregon Public Utility Commission |
| Decision | Settlement approved; publicly reported on 13 November 2026 |
| Effective | 1 January 2027 (as reported) |
| Scope | Data centers of 20 MW or more served by Pacific Power (PacifiCorp) in Oregon |
Key changes in the Oregon data center tariff
- A separate customer class. Computing, data processing and web hosting loads of 20 MW or more move into a dedicated class rather than sharing costs with other commercial users.
- Direct cost assignment. The infrastructure and services needed to serve these customers are assigned to them, not spread across residential and small business bills, according to the PUC.
- Long-term service agreements. Large data centers must sign long-term contracts with the utility, a tool designed to protect other customers if a project leaves or under-uses capacity.
- A 1 cent per kWh surcharge on very large data centers. The PUC says the revenue will fund energy efficiency, essential home repairs and distributed energy resources for low-income customers.
- Emissions safeguards. The framework includes provisions so that new large loads do not undermine Oregon’s emissions targets.
Detailed terms such as minimum demand charges, contract length and collateral were not set out in the public summaries we reviewed. Developers should read the final tariff sheets when Pacific Power files them.
Who is affected
Data center developers and hyperscalers planning sites in Pacific Power’s Oregon territory face higher upfront commitments but clearer rules. Residential and small business customers are the intended beneficiaries, since the framework aims to stop data center growth from raising their rates. The settlement was supported by Pacific Power, PUC staff and the Oregon Citizens’ Utility Board, with other parties also participating.
How it compares with PGE’s framework
Portland General Electric’s version, approved in May 2026 under Order No. 26-154, gives a useful benchmark. It created Schedule 96 for loads above 20 MW, required those customers to cover 100% of distribution upgrades, and set generation and transmission minimum demand charges at 90% of contracted capacity. Contract terms run from 10 years up to 30 years for loads of 220 MW or more, and a 1 cent per kWh surcharge applies to projects over 100 MW. Pacific Power’s framework follows the same logic, so investors should expect broadly similar economics across Oregon’s two largest investor-owned utilities.
Timeline
- 2025: Oregon passes HB 3546, the POWER Act, directing the PUC to address cost allocation for large data centers.
- 7 May 2026: PUC approves PGE’s large-load framework (Order No. 26-154).
- Mid-November 2026: PUC approves the Pacific Power settlement in UE 463.
- 1 January 2027: Reported effective date for the Pacific Power framework.
Impact on the industry and investors
Oregon has become a major data center destination, and the two rulings put it among the early states to apply full cost-causation rules to hyperscale load. For developers, the trade-off is higher committed costs in exchange for regulatory certainty and a lower risk of political backlash over residential bills. For utilities, long-term contracts reduce the risk of stranded investment in new substations and lines.
The ruling also fits a national pattern. Grid operators and utilities in other regions have filed large-load interconnection and tariff proposals at FERC this month, as covered in our analysis of PJM’s large-load filing. Programs that shift costs toward large users while funding customer-side resources, such as New Jersey’s PowerUp NJ order, point in the same direction.
The risk for the sector is that stricter terms push some projects to states with lighter rules. The opportunity is that predictable tariffs may make Oregon projects easier to finance.
Compliance: what to watch
- Pacific Power’s compliance tariff filing and final schedule terms, including minimum bills and security requirements.
- The exact load threshold that triggers the 1 cent per kWh surcharge for “very large” facilities.
- How existing data centers and projects already in the interconnection queue are treated.
- Further PUC dockets on new-load connection costs that could tighten terms again.
FAQ
Which data centers fall under the new Pacific Power rules?
Computing, data processing and web hosting customers with loads of 20 MW or more in Pacific Power’s Oregon service area.
When does the framework start?
It is reported to take effect on 1 January 2027, subject to the utility’s compliance filings.
Will residential bills go down?
The framework is designed to keep data center costs off other customers’ bills rather than to cut existing rates, and part of the surcharge funds programs for low-income households.
Official source