The rules for plugging data centers and other giant electricity users into America’s power grid are being rewritten. The latest milestone in FERC large load interconnection reform came on November 16, 2026, when PJM Interconnection, the country’s largest grid operator, filed new tariff language with the Federal Energy Regulatory Commission (FERC) in response to a June show cause order. For utilities, developers, hyperscalers and energy investors, the filings now arriving at FERC will shape how fast large loads connect, who pays for grid upgrades and what technical standards new facilities must meet.
| At a glance | |
|---|---|
| Name / number | Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,211 (PJM: Docket No. EL26-67-000); PJM response filing, Docket No. ER27-522-000 |
| Issuing authority | Federal Energy Regulatory Commission (FERC); filing by PJM Interconnection, L.L.C. |
| Date issued | Show cause orders: June 18, 2026. PJM filing: November 16, 2026 |
| Effective date | PJM requests January 16, 2027 (subject to FERC acceptance); a separate concurrent PJM filing proposes March 16, 2027 for other changes |
| Scope | Six regional grid operators (PJM, MISO, SPP, CAISO, ISO New England, NYISO) and their transmission owners; large commercial and industrial loads such as AI data centers |
Background: why FERC acted on large loads
The proceeding traces back to October 23, 2025, when Energy Secretary Chris Wright used Section 403 of the Department of Energy Organization Act to send FERC a proposed rulemaking (an advance notice of proposed rulemaking, Docket No. RM26-4) on connecting large loads to the transmission system. DOE’s proposal centered on loads of 20 MW and above.
Rather than issue a single national rule, FERC on June 18, 2026 opened six separate proceedings under Section 206 of the Federal Power Act, one for each regional transmission organization (RTO) or independent system operator (ISO). Each operator and its transmission owners were told to either show that their existing tariffs remain just and reasonable for large loads, or explain what tariff changes would fix the concerns FERC identified. The generic RM26-4 docket was left open for possible future action on utilities outside organized markets.
We have tracked the power demands of AI for months, including in AI’s escalating energy needs and the regulatory controversy they triggered. The FERC process is the first coordinated federal attempt to turn that debate into enforceable grid rules.
Key changes in the FERC large load interconnection proceeding
- A working definition of “large load.” In the PJM order, FERC said it appears reasonable to define a large load as a new commercial or industrial customer at a single site with peak demand of 50 MW or more, interconnected above 69 kV and not part of a co-location arrangement. This is a preliminary finding, not a final rule.
- Faster studies and more transparency. According to law firm analyses of the orders, FERC signaled that large-load studies should take no more than 60 to 90 days and that operators should publish data on large-load additions and network upgrade cost estimates.
- Co-location and netting. The orders addressed generation located next to, or serving, large loads, and questioned arrangements that let customers net on-site generation against demand to reduce transmission charges.
- New service options. The orders contemplated interim network service while upgrades are built, plus firm and non-firm contract demand services for flexible loads.
- Resource adequacy reporting. Each operator had to file an informational report on generation adequacy for existing and new large loads within 30 days.
What PJM filed on November 16
PJM’s Section 205 filing, titled a proposal to address operational requirements for “Large Computational Load” and establish an annual transmission service reporting requirement, adds a new tariff category. A Large Computational Load is defined as a Large Load containing 25 MW or more of maximum load served through power electronic conversion equipment, a configuration common in AI data centers. PJM’s base Large Load threshold of 50 MW cumulative peak at a single site was accepted by FERC effective October 12, 2026.
The filing sets minimum voltage and frequency ride-through requirements, with technical details to be placed in PJM Manuals. Other operational topics, including ramp rates, telemetry and remote disconnection, are established as a framework, with manual language to be developed in 2027. PJM would also publish an annual report on network integration transmission service (NITS), interim NITS and firm and non-firm contract demand service. The requirements would apply to new projects, materially modified projects and, on a transitional basis, existing facilities. PJM asked FERC for a 60-day comment period.
Who is affected
- Data center developers and hyperscalers seeking grid connections in the 13-state PJM footprint and other RTO regions.
- Transmission owners and utilities, which must update tariffs, cost recovery and credit requirements.
- Independent power producers pursuing co-location deals with large loads.
- Retail ratepayers and state regulators, who are focused on whether grid upgrade costs shift to households.
Timeline
| Date | Milestone |
|---|---|
| Oct 23, 2025 | DOE sends large-load ANOPR to FERC (RM26-4) |
| Jun 18, 2026 | FERC issues six Section 206 show cause orders |
| Aug 14, 2026 | FERC grants PJM a 90-day abeyance (196 FERC ¶ 61,129) |
| Oct 12, 2026 | PJM 50 MW Large Load definition takes effect |
| Oct 28, 2026 | CAISO Board approves its large-load proposal |
| Nov 16, 2026 | Response deadline; PJM files ER27-522-000 |
| Dec 16, 2026 | Answers due in the PJM show cause docket |
| Jan 16, 2027 | PJM’s requested effective date |
Impact on the industry and investors
For developers, clearer study timelines could reduce the uncertainty that has slowed many data center projects. At the same time, ride-through standards, telemetry and remote disconnection requirements add equipment costs, and stricter credit support tied to requested megawatts raises the capital needed up front. For investors, the proceedings reward projects with firm interconnection positions, flexible load designs and on-site generation that fits the new co-location rules. Regional differences will matter: CAISO, for example, approved a proposal on October 28, 2026 that also uses a 50 MW threshold and offers a flexible interim interconnection option. Readers following AI-driven demand can also see our earlier coverage of managing energy needs in the age of AI.
Compliance: what to watch
- Comments and protests on PJM’s ER27-522-000 filing and FERC’s decision on the January 16, 2027 effective date.
- Responses from the other RTOs and how closely they align on thresholds, cost allocation and co-location.
- Updates to PJM Manuals in 2027 that will contain the detailed technical standards.
- Any further action in the generic RM26-4 docket for non-RTO utilities.
FAQ
What is a large load under FERC’s show cause orders?
FERC preliminarily described it as a new commercial or industrial customer at a single site with peak demand of at least 50 MW, connected above 69 kV and not co-located with generation.
Is PJM’s Large Computational Load rule already in effect?
No. PJM filed it on November 16, 2026 and requested a January 16, 2027 effective date. FERC must still accept it.
Does the FERC process create a single national rule?
Not yet. FERC chose region-by-region Section 206 proceedings, while keeping the generic RM26-4 docket open for possible future action.
Official source
FERC order in Docket No. EL26-67-000 (June 18, 2026), as posted by PJM: FERC show cause order (PDF). PJM filing in Docket No. ER27-522-000: PJM November 16, 2026 filing (PDF). FERC eLibrary: elibrary.ferc.gov.